Pincher Creek council approves $528K to secure clean, reliable water supply

Pincher Creek town council has approved $528,000 in funding to replace aging sand filter media at the water treatment plant, addressing infrastructure that has exceeded its expected lifespan and is affecting plant operations.

The decision was made during the March 9 regular council meeting, with funding to come from the town’s utility reserve.

Administration brought the request forward citing the deteriorating condition of the sand media, which plays a critical role in the water treatment process by filtering out remaining particles after initial settling.

According to administration, the existing sand media has been in place since the plant was constructed more than three decades ago. While the typical lifespan of such media is 20 to 25 years, Pincher Creek’s system has continued operating for 36 years and has never been replaced since the plant was constructed, largely due to the efforts of plant operators.

However, officials said the extended use is now beginning to impact performance.

As the sand ages, its ability to effectively filter water declines, requiring the plant to slow production in order to maintain water quality. This has resulted in longer operating hours and increased strain on staff, who have been working extended shifts, including nights and weekends, to keep up with demand.

Administration indicated to council that replacing the sand media before further decline is critical to maintaining both efficiency and reliability in the system.

Mayor Wayne Oliver described the replacement as part of routine but essential maintenance to ensure the continued safety and quality of the town’s drinking water.

Event flyer for The Hometown Holiday Market on November 14, 2026, at the Heritage Inn in Pincher Creek, featuring a list of vendors and event details set against a snowy holiday background.

He explained that raw water is drawn from the Castle River and, when conditions allow, from the Pincher Creek, before being stored in a large reservoir that provides a backup supply for the community. From there, water enters the treatment plant, where it undergoes multiple stages of purification.

A key step in that process is sand filtration.

“You put the raw water through the sand and the sand captures any particulate that’s in the water,” Oliver said, noting that this filtration occurs before the water moves through additional treatment phases.

Chief administrative officer Konrad Dunbar expanded on the process, outlining how water is treated once it enters the facility.

“The water is stored in a reservoir before going into the plant. In the plant it first goes through the floc cells, for initial settling treatment (removing any large floating particles), then through the sand filters to filter out any remaining particles, next is the UV treatment for initial disinfection,” Dunbar explained.

Chlorine is added in the final stage to ensure continuous disinfection as water is distributed through the system. Dunbar compared the sand filters to household air filters.

“They catch particles to make the water clean, but like any filter, they require maintenance and eventual replacement,” he said, noting the system uses multiple types and sizes of specialized sand.

“Our mandate is to provide clean, uninterrupted drinking water to our residents,” Dunbar added.

Announcement for Family Violence Prevention Month flag raising event on November 17 at 10 a.m. outside the Pincher Creek Library, hosted by the Pincher Creek Women’s Emergency Shelter Association.

Council heard that while a project of this scale would typically be considered during the annual budget process, administration chose to bring it forward now due to recently secured external funding.

The project has received support through the Alberta Municipal Water/Wastewater Partnership program, which will cover about 52 per cent of the total cost. While replacing all three filter cells is estimated at about $1.1 million, the grant reduces the municipality’s share to $528,000.

Administration noted that only two of the three filters are currently required to meet demand.

A final decision on the scope of the work will be made following detailed engineering analysis and the tendering process, which will assess whether it is more cost-effective to replace all three filters while grant funding is available.

The town’s utility reserve, which will fund the project, currently sits at about $1.84 million and is expected to increase following year-end financial updates.

Dunbar said the next steps include engineering design, tendering and installation, with the overall timeline estimated at four to six months, though that may evolve as the project progresses.

The town does not anticipate any disruption to water service during construction.

“It is our intention to not disrupt water to our residents at all,” Dunbar said, adding that residents will be notified immediately if any unforeseen issues arise.

 

Strong local journalism matters to Canadian communities

This article was reported and written by Shootin’ the Breeze’s Local Journalism Initiative reporter. 

The Local Journalism Initiative is a federally funded program that supports original public-interest journalism in smaller or underserved communities across Canada. Content produced through the initiative is editorially independent and may be shared by other Canadian media outlets.

Stories like this are reported to keep readers informed and connected — and to reflect real Canadian life.

 

Alberta | AB, Municipal Councils | Governments