Aging bridges and failing culverts take priority in MD of Pincher Creek’s 2026 capital budget. More than $3 million earmarked for road and water crossings.

MD of Pincher Creek approves $4.5M capital budget for 2026

December 7, 2025
Somya Lohia | Local Journalism Initiative Reporter | Shootin’ the Breeze

The Municipal District of Pincher Creek has approved a $4.58-million capital budget for 2026 that puts aging bridges and failing culverts at the centre of its spending plan, with more than two-thirds of the money earmarked for critical road and water crossings.

Council adopted the spending plan on Nov. 25, pairing it with the MD’s operating budget and income statement, which outline how day-to-day services, from planning to waste collection, will be funded in the year ahead.

While the capital plan concentrates on major infrastructure, the operating budget highlights continuing pressures tied to inflation, insurance rates, equipment maintenance and rising service demands.

Income statement and revenues

The MD’s 2025 financial results show continued reliance on a mix of property taxes, user fees and government transfers to fund municipal operations.

Property taxes remained the primary revenue source, generating $16,383,475, which was $2,014,625 above the budgeted amount of $14,368,850.

This, along with other sources of income made total revenues of $17,637,990, surpassing the 2025 budgeted revenue of $16,466,810.

Total expenses for the year held steady at $10,169,553. When including $323,460 in government transfers for capital projects, the MD recorded a total excess of revenue over expenses of $7,791,897 for 2025, surpassing the budgeted projection of $5,356,010.

Looking ahead, the 2026 consolidated budget projects net municipal tax revenue of $16,385,140, forming the foundation of the MD’s anticipated income. Additional operating revenues are expected to include $14,648,680 from property taxes, $446,510 from user fees and sales of goods, $551,870 from government transfers for operating purposes, and $350,000 in investment income.

Projected expenses for 2026 are $13,706,885. Including $1,409,000 in government transfers for capital, the MD anticipates a total excess of revenue over expenses of $4,087,255, indicating a decrease from the 2025 surplus.

Operational variances by department

The 2026 budget outlines several operational shifts across municipal departments, driven by the conclusion of grant-funded studies and changing infrastructure costs.

Public works expenses are budgeted to rise to $6,220,900 in 2026, reflecting higher costs for road maintenance and crushing operations. Departmental revenue is projected to decline by $171,390 to $295,800, primarily due to the conclusion of the Alberta Community Partnership grant that funded the previous year’s road study.

Administrative services revenue is forecast to increase by $187,700 to $254,330, following successful ACP funding for a new facilities assessment. Correspondingly, administrative expenses are set to rise to $2,761,930 to cover the costs of the assessment project.

Planning and development anticipates a revenue drop of $76,000 with the expiration of Federation of Canadian Municipalities funding for the brownfield study. While completing the study yields some savings, expenses are budgeted at $404,660 to support updates to the Oldman River Reservoir area structure plan and higher contract fees from the Oldman River Regional Services Commission.

Water services expenses are expected to decrease by $112,265 to $856,395, reflecting the completion of studies on the Cridland Dam and the drought projects assessment. These savings are partially offset by required repairs to the Lundbreck Reservoir. Revenue is projected to increase by $20,860 to $343,860 due to updates to the utility bylaw and the near completion of the drought projects assessment.

Waste management revenue is projected to increase by $56,925 to $78,925, supported by a contract with Circular Materials. However, departmental expenses are expected to rise to $375,580 due to higher fees and increased usage rates.

Community services expenses are budgeted to decrease to $574,395, largely due to the cessation of payments to the Pincher Creek Community Early Learning Centre. Revenue is projected to decline by $100,000 to $111,620.

Airport operations will see expenses rise by $44,550 to $132,250 to fund an airport loading analysis, with expected revenue of $62,750.

Law enforcement revenue is projected to nearly double to $40,150 as the municipality begins collecting ticket revenue.

Wastewater services costs are expected to increase to $182,600, driven primarily by repairs to the lift station’s air handling unit.

Overall, the MD projects a deficiency of revenue over expenses of $12,417,620 for 2026, reflecting the combined impact of operational changes, project completions, and shifting departmental revenues and expenses.

Capital spending continues to dominate attention

Council adopted the 2026 spending plan, directing the bulk of next year’s capital work toward infrastructure that staff say is approaching the end of its life cycle and, in several cases, already showing signs of structural failure.

A series of major culvert replacements, bridge engineering projects and road repairs account for more than $3 million of the overall budget.

The largest allocations include culvert replacements on Connelly Road, Waldron Flats, West Maycroft and Olin Creek, all identified as priority sites due to deterioration, inadequate capacity or erosion concerns.

Work for the Skyline Road and Twin Butte Road structures is also included, with the latter addressing issues on a more than 100-year-old bridge shared with Cardston County.

Southfork Road returns to the capital plan with funds set aside for design work and land acquisition. Administration noted that construction is expected to follow in later years once engineering and property requirements are complete.

Other significant projects include rehabilitation work at Therriault Dam, wastewater line replacement in Lundbreck and continued upgrades tied to the MD’s infrastructure management plan.

Equipment and fleet renewal also forms a notable portion of the budget. The MD intends to purchase a grader, a plow truck, a water truck, a heavy truck, a loader scale, welding equipment and a rotary cutter, along with a purchase of a three-quarter-ton truck and one-ton truck, cab and chassis. Total projected cost is $1,408,000.

Replacement of the financial software system is projected to cost $85,000.

Administration reported that several projects deferred in previous years will move forward under the 2026 plan, while others, such as full Southfork Road reconstruction, will be funded through future capital cycles. Long-term planning documents show infrastructure needs rising sharply through 2030, particularly for bridges and major roadwork.

Overall, the grand total expenditure for 2026 is projected to be $4,582,200. The MD plans to finance the 2026 capital program without new borrowing. Instead, $3,173,000 will come from reserves, supported by $1,409,000 in grant funding.

Construction timelines and tendering will be finalized early in the new year, with most work expected to begin as soon as weather allows. Residents may experience temporary traffic disruptions in areas where culvert replacements and bridge work are scheduled.

 

Strong local journalism matters to Canadian communities

This article was reported and written by Shootin’ the Breeze’s Local Journalism Initiative reporter.

The Local Journalism Initiative is a federally funded program that supports original public-interest journalism in smaller or underserved communities across Canada. Content produced through the initiative is editorially independent and may be shared by other Canadian media outlets.

Stories like this are reported to keep readers informed and connected — and to reflect real Canadian life.

 

 

Event poster for a Secondhand Dreamcar concert at the Empress Theatre on November 20, 2026, at 7:30 PM, featuring a photo of the band members.
A banner promoting local journalism in Canada, highlighting Shoot the Breeze’s community-focused reporting, partners, government funding, awards, and the Alberta Weekly Newspapers Association logo.
Leave a Reply

Southwest Alberta News, Features and Events

Shootin' the Breeze connection to more local stories
Aging bridges and failing culverts take priority in MD of Pincher Creek’s 2026 capital budget. More than $3 million earmarked for road and water crossings.

MD of Pincher Creek approves $4.5M capital budget for 2026

December 7, 2025
Somya Lohia | Local Journalism Initiative Reporter | Shootin’ the Breeze

The Municipal District of Pincher Creek has approved a $4.58-million capital budget for 2026 that puts aging bridges and failing culverts at the centre of its spending plan, with more than two-thirds of the money earmarked for critical road and water crossings.

Council adopted the spending plan on Nov. 25, pairing it with the MD’s operating budget and income statement, which outline how day-to-day services, from planning to waste collection, will be funded in the year ahead.

While the capital plan concentrates on major infrastructure, the operating budget highlights continuing pressures tied to inflation, insurance rates, equipment maintenance and rising service demands.

Income statement and revenues

The MD’s 2025 financial results show continued reliance on a mix of property taxes, user fees and government transfers to fund municipal operations.

Property taxes remained the primary revenue source, generating $16,383,475, which was $2,014,625 above the budgeted amount of $14,368,850.

This, along with other sources of income made total revenues of $17,637,990, surpassing the 2025 budgeted revenue of $16,466,810.

Total expenses for the year held steady at $10,169,553. When including $323,460 in government transfers for capital projects, the MD recorded a total excess of revenue over expenses of $7,791,897 for 2025, surpassing the budgeted projection of $5,356,010.

Looking ahead, the 2026 consolidated budget projects net municipal tax revenue of $16,385,140, forming the foundation of the MD’s anticipated income. Additional operating revenues are expected to include $14,648,680 from property taxes, $446,510 from user fees and sales of goods, $551,870 from government transfers for operating purposes, and $350,000 in investment income.

Projected expenses for 2026 are $13,706,885. Including $1,409,000 in government transfers for capital, the MD anticipates a total excess of revenue over expenses of $4,087,255, indicating a decrease from the 2025 surplus.

Operational variances by department

The 2026 budget outlines several operational shifts across municipal departments, driven by the conclusion of grant-funded studies and changing infrastructure costs.

Public works expenses are budgeted to rise to $6,220,900 in 2026, reflecting higher costs for road maintenance and crushing operations. Departmental revenue is projected to decline by $171,390 to $295,800, primarily due to the conclusion of the Alberta Community Partnership grant that funded the previous year’s road study.

Administrative services revenue is forecast to increase by $187,700 to $254,330, following successful ACP funding for a new facilities assessment. Correspondingly, administrative expenses are set to rise to $2,761,930 to cover the costs of the assessment project.

Planning and development anticipates a revenue drop of $76,000 with the expiration of Federation of Canadian Municipalities funding for the brownfield study. While completing the study yields some savings, expenses are budgeted at $404,660 to support updates to the Oldman River Reservoir area structure plan and higher contract fees from the Oldman River Regional Services Commission.

Water services expenses are expected to decrease by $112,265 to $856,395, reflecting the completion of studies on the Cridland Dam and the drought projects assessment. These savings are partially offset by required repairs to the Lundbreck Reservoir. Revenue is projected to increase by $20,860 to $343,860 due to updates to the utility bylaw and the near completion of the drought projects assessment.

Waste management revenue is projected to increase by $56,925 to $78,925, supported by a contract with Circular Materials. However, departmental expenses are expected to rise to $375,580 due to higher fees and increased usage rates.

Community services expenses are budgeted to decrease to $574,395, largely due to the cessation of payments to the Pincher Creek Community Early Learning Centre. Revenue is projected to decline by $100,000 to $111,620.

Airport operations will see expenses rise by $44,550 to $132,250 to fund an airport loading analysis, with expected revenue of $62,750.

Law enforcement revenue is projected to nearly double to $40,150 as the municipality begins collecting ticket revenue.

Wastewater services costs are expected to increase to $182,600, driven primarily by repairs to the lift station’s air handling unit.

Overall, the MD projects a deficiency of revenue over expenses of $12,417,620 for 2026, reflecting the combined impact of operational changes, project completions, and shifting departmental revenues and expenses.

Capital spending continues to dominate attention

Council adopted the 2026 spending plan, directing the bulk of next year’s capital work toward infrastructure that staff say is approaching the end of its life cycle and, in several cases, already showing signs of structural failure.

A series of major culvert replacements, bridge engineering projects and road repairs account for more than $3 million of the overall budget.

The largest allocations include culvert replacements on Connelly Road, Waldron Flats, West Maycroft and Olin Creek, all identified as priority sites due to deterioration, inadequate capacity or erosion concerns.

Work for the Skyline Road and Twin Butte Road structures is also included, with the latter addressing issues on a more than 100-year-old bridge shared with Cardston County.

Southfork Road returns to the capital plan with funds set aside for design work and land acquisition. Administration noted that construction is expected to follow in later years once engineering and property requirements are complete.

Other significant projects include rehabilitation work at Therriault Dam, wastewater line replacement in Lundbreck and continued upgrades tied to the MD’s infrastructure management plan.

Equipment and fleet renewal also forms a notable portion of the budget. The MD intends to purchase a grader, a plow truck, a water truck, a heavy truck, a loader scale, welding equipment and a rotary cutter, along with a purchase of a three-quarter-ton truck and one-ton truck, cab and chassis. Total projected cost is $1,408,000.

Replacement of the financial software system is projected to cost $85,000.

Administration reported that several projects deferred in previous years will move forward under the 2026 plan, while others, such as full Southfork Road reconstruction, will be funded through future capital cycles. Long-term planning documents show infrastructure needs rising sharply through 2030, particularly for bridges and major roadwork.

Overall, the grand total expenditure for 2026 is projected to be $4,582,200. The MD plans to finance the 2026 capital program without new borrowing. Instead, $3,173,000 will come from reserves, supported by $1,409,000 in grant funding.

Construction timelines and tendering will be finalized early in the new year, with most work expected to begin as soon as weather allows. Residents may experience temporary traffic disruptions in areas where culvert replacements and bridge work are scheduled.

 

Strong local journalism matters to Canadian communities

This article was reported and written by Shootin’ the Breeze’s Local Journalism Initiative reporter.

The Local Journalism Initiative is a federally funded program that supports original public-interest journalism in smaller or underserved communities across Canada. Content produced through the initiative is editorially independent and may be shared by other Canadian media outlets.

Stories like this are reported to keep readers informed and connected — and to reflect real Canadian life.

 

 

A woman sorts food items into cardboard boxes at a food bank, with text above advertising Vision Credit Union’s Helping Hand Grants, which offer up to $10,000 for rural Alberta non-profits, with a QR code and an application deadline of January 17, 2027.
Leave a Reply

Southwest Alberta News, Features and Events

Alberta and Beyond News, Features and Events

Announcement for Family Violence Prevention Month flag raising event on November 17 at 10 a.m. outside the Pincher Creek Library, hosted by the Pincher Creek Women’s Emergency Shelter Association.
Shootin' the Breeze ad for free trial subscription